A. Installation of steam pipe lines
B. Installation of Ammonia pipe lines
C. Rehabilitation of boilers 9 Ton .
D. Rehabilitation of boilers 3 Ton .
E. Rehabilitation of boilers 7،5 Ton .

NPA work for farm frites new operating planet (2018 – 2019)

– Installation boiler 20 tons.

– Installation production lines & machinery.

– Installation utilities piping network ( steam – water – compressed air ).

 –  Grouses piping network.

– Oil tanks & oil system.

– Refrigeration system.

– H vac system.

– Firefighting system ( tank – piping – pump room ).

– Bunkers and potato receiving system.